275/132kV main intake substation completed by Al Khairi Development
Power & Energy · Selangor

275/132kV Main IntakeSubstation.

Complete civil, structural and earthing works for a strategic transmission intake serving an industrial corridor of more than 180,000 consumers — delivered 34 days ahead of contract programme with zero lost-time injuries.

  • Design & Build
  • CIDB G7
  • TNB technical specification
  • Live-site interface
Client
Tenaga Nasional Berhad
Location
Shah Alam, Selangor
Contract value
RM 48.6 million
Period
Mar 2021 – Nov 2023
Status
Completed & energised
34daysAhead of programme
0Lost-time injuries
98.4%First-time inspection pass
1.2MSafe man-hours worked
Project overview

A transmission asset built to run for fifty years.

The intake substation sits at the junction of two 275kV transmission corridors and steps supply down to the 132kV distribution network feeding an industrial belt in central Selangor. Al Khairi Development was appointed for the full civil and structural package: site formation, deep foundations, transformer plinths and firewalls, cable trenching, control building, and the complete earthing grid.

The site was a partially reclaimed former quarry with variable rock head and a perched water table — the ground investigation returned SPT values swinging between 4 and refusal within twenty metres. Rather than absorb that risk into the programme, we re-engineered the foundation solution during the tender clarification stage and carried the redesign through to authority approval.

Works were executed alongside an operating 132kV switchyard. Every crane lift, excavation and cable pull was sequenced against live outage windows agreed with the client’s asset team, with permit-to-work discipline enforced daily.

Handed over 34 days early with an as-built defect list of eleven minor items, all closed within the first month of the DLP.

Scope of works.

Five work packages delivered under a single lump-sum contract, self-performed except for specialist piling and high-voltage terminations.

01

Site formation & earthworks

Bulk cut-and-fill across 4.8 hectares of reclaimed quarry, including rock breaking, engineered fill in 300 mm compacted layers, and a permanent gravity retaining structure along the eastern boundary.

  • 112,000 m³ earthworks
  • Rock breaking
  • RC retaining wall 6.5 m
  • Slope protection
02

Piling & transformer foundations

Bored piles socketed into rock supporting transformer plinths designed for 168-tonne units, with seismic restraint detailing and oil-containment bunds sized to full transformer volume plus rainfall allowance.

  • 486 bored piles
  • Ø600–900 mm
  • Oil containment bunds
  • Blast firewalls
03

Control building & switchgear hall

Two-storey reinforced-concrete control building housing protection and control panels, battery rooms, and a switchgear hall with raised access flooring, fire suppression, and redundant HVAC.

  • 2,140 m² built-up
  • Raised access floor
  • FM-200 suppression
  • N+1 HVAC
04

Earthing grid & cable systems

Full station earthing grid designed to keep step-and-touch potentials within IEEE 80 limits, verified by fall-of-potential testing, plus 11 km of cable trenching, troughs, and duct banks.

  • IEEE 80 compliance
  • 11 km cable route
  • Copper grid & risers
  • Fall-of-potential testing
05

External works & commissioning support

Perimeter security, access roads to heavy-transport loading, stormwater detention sized to MSMA requirements, and civil standby throughout the client’s testing and energisation programme.

  • MSMA-compliant drainage
  • Heavy-haul access road
  • Security perimeter
  • Energisation standby

On site.

Progress photography from formation through to energisation. Images are placeholders for the mockup.

Completed switchyard with transformer bays energised
Switchyard, post-energisationTransformer bays and gantry structures at practical completion.
Control building structural frame under construction
Control buildingRC frame topped out, month 14.
Heavy-haul access road constructed for transformer delivery
Heavy-haul accessRoad built to carry 168-tonne transformer deliveries.
Stormwater detention and drainage works on the substation perimeter
Detention pondMSMA-compliant stormwater attenuation on the north boundary.
Delivery programme

Thirty-two months, held.

The programme was rebaselined once, at month six, after the foundation redesign was approved. Every milestone after that was met or beaten.

  1. Mar 2021

    Award & mobilisation

    Site possession, temporary works, and the ground investigation that triggered the foundation review.

  2. Sep 2021

    Foundation redesign approved

    Bored piles replaced the tendered pad footings. Authority approval obtained without extension of time.

  3. Apr 2022

    Transformer plinths complete

    All plinths, bunds and firewalls handed to the client’s electrical contractor two weeks early.

  4. Jan 2023

    Control building topped out

    Structure, envelope and building services complete; raised flooring and panel bases released for fit-out.

  5. Aug 2023

    Earthing grid verified

    Fall-of-potential testing confirmed step-and-touch potentials inside IEEE 80 limits on first attempt.

  6. Nov 2023

    Energised & handed over

    Practical completion issued 34 days ahead of contract date. Eleven minor defects, all closed within 30 days.

Engineering response

Three problems worth naming.

Every project has them. What matters is whether they are surfaced early and priced honestly, or discovered late and argued about.

Challenge 01

Variable rock head across a reclaimed quarry

SPT values swung from 4 to refusal within twenty metres. Tendered pad footings would have carried unacceptable differential settlement risk under 168-tonne transformers.

Response: bored piles socketed into competent rock, redesigned and approved in month six with no extension of time claimed.

Challenge 02

Building beside a live 132kV switchyard

No outage was available for the first eighteen months. Crane radii, excavation lines and cable pulls all had to respect live-apparatus clearance envelopes.

Response: daily permit-to-work regime, exclusion zones surveyed and physically marked, and lift plans reviewed with the client’s asset team weekly.

Challenge 03

Monsoon exposure on an open platform

Two north-east monsoon seasons fell inside the programme, with the platform fully stripped and vulnerable to washout and silt discharge.

Response: staged formation with early permanent drainage, silt traps commissioned ahead of bulk earthworks, and zero DOE non-compliance notices received.

Technical particulars.

Extracted from the as-built record and the handover dossier issued to the client.

Key quantities and standards
ItemParticularsStandard / reference
Structural concreteGrade 40 & 50, sulphate-resisting to substructureMS EN 206-1
ReinforcementB500B high-yield deformed bar, 2,310 tMS 146:2014
Bored piles486 nos, Ø600–900 mm, rock-socketedBS EN 1536
Earthing gridBare copper 120–240 mm², exothermic jointsIEEE 80-2013
Oil containmentBunded to 110% transformer volume + rainfallTNB technical spec
StormwaterDetention pond, 50-year ARI attenuationMSMA 2nd Edition
Fire protection4-hour blast firewalls; FM-200 in control roomsUBBL 1984
Quality regimeITP-driven inspection, 98.4% first-time passISO 9001:2015
The civil package was the part of this scheme we worried about least. Their team flagged the ground risk before we did, redesigned it properly, and never once asked us to absorb the consequence of their own programme.
Project DirectorTransmission Projects Division · Client representative